Safety stock

Size a buffer that protects against demand swings during supplier lead time.

Built and maintained by The NumberPrism Editorial TeamEditorial policy

Your details

units
units
days
Results update as you type. The formula and assumptions are explained below the calculator.

Safety stock

74 units

Target cycle service level95.0%
Stockout risk per cycle5.0%
Demand during lead time560 units
Reorder point with this buffer634 units

Estimate only. It assumes normally distributed, independent daily demand; variable lead times need a larger buffer or a separate model.

Share calculator

Use this tool

Embed

How to calculate safety stock

Set a buffer from variability and service level.

1

Choose a service level

Higher levels reduce stockouts but raise holding cost.

2

Measure variability

Use the daily demand standard deviation from a representative period.

3

Enter lead time

The buffer grows with the square root of lead time, so shorter lead times reduce stock.

What does this tool do?

Safety stock is the extra inventory kept to absorb demand above forecast or a late delivery. The statistical approach scales the buffer with demand variability, lead time and the cycle service level you want to hit.

The Formula

Safety stock = Z × Daily demand standard deviation × √Lead time

Frequently Asked Questions

Which service level should I choose?

95% is a common balance for everyday products. Use a higher level for critical parts or high-margin items, and a lower level for cheap, slow-moving stock.

How do I estimate demand variability?

Use the standard deviation of daily demand over a recent period with similar seasonality. Include stockouts carefully, because missing sales understate true demand.